The Root River's North Branch takes an unnatural twist to the north at the site of a former hydroelectric dam. The river channel originally curved to the right – now mostly grown over with trees. (Photo by Dan Brown)
To End Erosion At A Former Dam, Engineers Shifting Root River Back To Its Original Bed
CAROLLTON TOWNSHIP, FILLMORE COUNTY — Each year, up to 40 dump truck loads of soil are stripped from the Root River’s banks and stream bottom at a remote oxbow northwest of Lanesboro.
The massive erosion – worst in high-flow years like 2024 – has altered the river bed, chewed up banks and smothered fish spawning gravel, according to river hydrology experts.
The blame for this ecological mess is a hydroelectric dam and power plant built in 1912-1915. Although abandoned decades ago, its harmful effects linger – just upstream of the Eagle Bluff Environmental Learning Center, where kids are taught about the outdoors and the environment.
Now, in one of the Driftless region’s most ambitious river restoration projects, engineers with excavating equipment intend to force the river back to where it belongs — or at least close to its original course. At a cost of nearly $1million, the 3,300-feet-long channel restoration aims to significantly reduce erosion in the Root River.
In high flows, the river’s unnatural twist at the site slams water into the north bank, eroding a private landowner’s property opposite Eagle Bluff.
“Right now, it does over a 90-degree bend and it doesn’t work at all,” said Geoffrey Griffin, CEO of G-Cubed, a Chatfield engineering firm hired to design and execute the restoration.
Based on historic aerial photos, Griffin estimated that 15 acres of land has been washed down the river so far. “That is just really unbelievable to see how much that river takes — just boom, boom, boom, literally another 10 feet of bank every year,” he added.
20th Century Progress, 21st Century Problem
The story of the North Branch’s massive erosion problem begins in 1912 when entrepreneurs started blasting a 1/3-mile-long tunnel through rock to create one of the area’s early hydropower plants.
It was an audacious project that took advantage of a giant oxbow, or horseshoe-shaped bend, on the river. On the upper oxbow, Brightdale Dam was built to direct river water into the tunnel. Turbines at the tunnel outlet supplied electricity to Preston and other towns.
Power generation at Brightdale ended in the mid-20th century, and the site later became Eagle Bluff Environmental Learning Center (ELC). The dam was removed in 2003. The old turbine house and tunnel remain and won’t be touched in the restoration effort.
The dam site is one of two serious erosion areas on the Eagle Bluff oxbow. Raging waters also eat away the environmental center’s property further downstream, frequently uprooting trees along the bank. After high flows, those trees become submerged hazards called “strainers” on a 3 1/2-mile stretch used for youth canoe classes.
“We can’t go down the river until we go through and make sure we have cleared out major strainers,” said Eagle Bluff Executive Director Colleen Foehrenbacher. “Staff have to go in the water with chainsaws. We’ve had tractors pulling out the trees.”
A separate $900,000 Root River bank-stabilization project on Eagle Bluff’s land will lower and strengthen the banks and recreate the floodplain.
The money for the work comes mostly from the Minnesota Environmental and Natural Resources Trust Fund, which gets proceeds of the Minnesota State Lottery. Fillmore County Soil and Water Conservation District and Eagle Bluff ELC are overseeing the two projects.
“This is huge,” said conservation district Administrator Dr. Riley Buley, who manages an array of conservation programs and participates in the multi-county Root River One Watershed One Plan. “The goal is to improve water quality and keep soil on the ground. This Brightdale project fits right into that and checks all the boxes.”
Hydrologist Jeff Weiss of the Minnesota Department of Natural Resources said the erosion at the Brightdale site and on Eagle Bluff property degrades the river far downstream. The Root River’s North Branch is classified as “impaired” for turbidity or suspended sediment.
“The sediment fills in pools, reducing their depth, and it can plug up culverts and make flooding worse,” said Weiss.
Fish and aquatic insects also suffer, Weiss said. The North Branch is known for smallmouth bass and other warm-water fish but also holds trout part of the year.
“Fish require clean gravel for spawning,” he added. “That can all be basically smothered by sedimentation.”
Construction Expected The Fall And Winter of 2024
The river restoration efforts are scheduled for this fall and winter which is unusually late in the year for Minnesota. The reason for the late start: bats.
The old hydro tunnel is now a designated bat hibernaculum, with four species living inside. DNR biologists advised waiting until the bats are inside for the winter which is usually about mid-October.
Both the dam site and Eagle Bluff projects require removal of trees that have grown up on the old river channel or banks. The harvested trunks will be embedded in banks for stability or fish habitat, Griffin and Foehrenbacher said.
At the former dam site, Griffin said, large excavators will dig a new, 3,300-feet-long channel on nearly the same path as the original riverbed. That work should be done in late December.
That channel initially will be left dry, with no flow from the river, so vegetation can take root along banks during the 2025 growing season. Then, in a grand finale, contractors plan in late summer 2025 to redirect the river’s flow into the reconstructed channel by shifting tons of rock and soil.
The bank-stabilization work downstream on the Eagle Bluff property will dramatically lower the 20-feet-high banks and spread soil over about 25 acres. It will be a major change to the landscape.
“During construction, it is going to be pretty upsetting with a lot of bare earth,” said Foehrenbacher. “We are going to end up restoring it to more native landscape. It is probably going to be an oak savannah.”
Timeline Of The Brightdale* Hydroelectric Plant And Its Consequences
Construction of what would become the Brightdale* power plant commenced in 1912. It remained in operation into the 1940s before being decommissioned. The power plant dam’s eventually removal in 2003 led to erosion and river channeling issues being addressed in 2024.
*An “s” later was added to the name, and the nearby state forest is called the Brightsdale Forest Management Unit.
Timeline sources: Root River Power & Light, A History by A.H. Hanning (1940), The Dairyland Power Story by Harvey Schermerhorn (1973), The Night They Turned on the Lights by Harold Severson (1962), Brightsdale Dam Channel Restoration by Nick Proulx and Jeff Weiss (2022 DNR report), G-Cubed.
…………………
Contributors
Writer: David Shaffer (pictured) is a retired Star Tribune reporter and editor, an active trout fisherman, cyclist and hiker who splits his time between Lanesboro and Tucson, Arizona.
Photographer: Dan Brown, @dartfishdan on Instagram